How to stop scheduling operation just before the shift ends

former_member819184
Discoverer
0 Kudos

Hi,


while scheduling the orders in APO, the orders starts scheduling just before the shift ends, in that case even if my operation is taking 2 hours to Complete, it get the end date as next date.

Do we have any option that if the resource capacity is not available to complete the on same day, the whole operation should shift to next day.


Thanks in advance..:fc2a7644-9ea4-4197-8a9e-0e5c39a96942.jpeg

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member819184
Discoverer
0 Kudos

Hi Anand,

It worked..

Thanks,

andy_yeri
Contributor
0 Kudos

Try using the SHIFT BREAK option on the PDS_MAINT t-code & change it to "0". Should work.