WHAT IS TCODE TO REPORT PROCESSING % NETWORK IN PROJECT SYSTEM

0 Kudos

Hi expert,

i was input data in CN25 field processing %, when i save it was succees but where tcode to see report that data after i input data processing % in CN25?

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

You can use CN41N and bring in percentage of work or duration.

0 Kudos

do you know, how to show up lastest proc % of work data in cn41n, so only data '50' that show? thank u mr

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Click on the Funnel icon, it is a filter.