The resourse capacity is not available during Process Order Creation Using T code: COR1

97 Views

Hi Gurus,

Not able to create Process order creation using T code: COR1,(allowing to create only one order for each calendar day, The order quantity can be 1No or 1000 No). After that when I am going to save the process order error message "The resourse capacity is not available" throughing. Screenshot attached.

  • Note:
  • I am able to create multiple Process orders on the same date when I am converting from plant order (ok)
  • In the plant no requirement for capacity planning.

Please help to resolve the issue.