Skip to Content
0

Work order dropping 1 month later

Feb 22, 2017 at 06:15 PM

127

avatar image

Guys,

I have a strategy based PM for 6 years and I choose Time- keydate(So,PM drops on the same date every 6 years) . The first Plan/Call date is 2016/03/14 and now when the next call is due, the Plan/call date is 2022/04/14 instead of 2022/03/14. I checked the maintenance packages in IP11 and it has no offsets. Can someone tell me why is this happening?

Thanks,

Nureya

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

4 Answers

Peter Atkin Feb 23, 2017 at 12:56 PM
0

Nureya,

Are you using shift factors, or the completion confirmation in your plan.

Also check your package sequence via IP13.

PeteA

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Feb 27, 2017 at 09:53 PM
0

Hi Nureya

Can you provide the shift factor values on the plan and actual completion dates on first call 2016/03/14

Thanks

Jey

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Mar 01, 2017 at 09:10 AM
0

Check whether the call horizon is 100% and the cycle modification factor is set to 1.

Check for the Shift factor tolerence as it relates to the order date being shifted to another date based on the tolerance value.


capture.jpg (41.0 kB)
Share
10 |10000 characters needed characters left characters exceeded
Nureya Miller Aug 18, 2017 at 09:57 PM
0

Thanks Guys for your help. Sorry i was out of job for a bit and now back in SAP again..so will need all your help. Thanks alot.

Share
10 |10000 characters needed characters left characters exceeded