How to consolidate multiple dependent requirements into a single purchase requisition during MRP run

markcarcione
Discoverer
0 Kudos

Dear MRP gurus,

We recently began using MRP to generate purchase requisitions for raw materials based on dependent requirements culminating from demand for the higher level finished goods. We're defining MRP type 'PD' and lot size key 'EX' for the raw materials.

Some of our raw materials have very long lead times (6 months). So, when we have multiple dependent requirements with dates that occur prior to the raw material lead time, multiple purchase requisitions are generated with the same delivery date (based on the lead time), which each p.req qty matching the dependent reqt qty.

We would prefer to only get one purchase requisition that will cover all of the dependent requirements up to the raw material lead time date.

Can we accomplish this with the standard MRP settings and config? And if so, what do we need to do differently?

Or, is there a way to convert the multiple purchase requisitions into a single PO line item without having multiple schedule lines, so the line item qty sums up to the individual qty of the multiple requisitions?

Thanks in advance!

Mark

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert

Hi Mark

You can define a period based lot sizing procedure that will combine all the requirements within a period and generate a single requisition. You can explore the lot-sizing procedure customizing, which allows you to have a different procedure for short-term and long-term horizon.

Regards,
Caetano

markcarcione
Discoverer

Thank you Caetano. Will work on setting this up and let you know how I make out. Appreciate the answer : )

pavansingineedi
Explorer
0 Kudos

create Bill of materials (BOM) for raw materials and maintain scheduling agreement with required dates and quantity and also maintain Source list with Agreement number and with MRP indicator 2. when you run the mrp it will create purchase req with all dependent requirements in single PR. Currently my client using this process for planned orders. you can use it for pr