Hello Experts,
In the current system (S4), per OVZ9, we have Without RLT unticked and With Purchase Orders ticked.
Please note, it is an external procurement (Procurement Type F)
And we know that, unticked Without RLT = telling the system to calculate Material Availability Date (MAD) per the material master fields: GR Processing Time, Planned Delivery time
Let me show the values related to them
Without RLT (unticked): GR Processing Time = 2 days; Planned Delivery time = 3 days;
So, we have 6 days (including Purchasing Processing Time = 1 day per configuration) to be considered to calculate Material Availability Date.
Include PO: created a PO with delivery date (29 days ahead) + Purchasing Processing Time = 1 day (per configuration) = total 30 days
Now, for sales order creation, the system has two options (6 days or 30 days) to calculate Material Availability Date (from Requested Delivery Date).
Per standard SAP, system is considering the earliest possible date (6 days per this example).
I may also have the values vice versa: Without RLT (30 days) and Include PO (6 days)
But the business wants the system to consider the longest/latest date to calculate MAD (Material Availability Date).
Please advise if this is achievable from configuration.