Skip to Content
0
Jul 14, 2022 at 08:08 AM

Project Systems -> Reverse settlement

166 Views Last edit Jul 14, 2022 at 11:09 AM 2 rev

I am doing the asset settlement reverse, however in the details list it does not takes the WBS element which is having a capitalization date.

to make it clear :

I have a project in which there are 2 WBS elements one is having a capitaliztion date of 12.02.2022 and the other one does not have a capitalization date.

The interest is calculated for 12 days for the one having capitalization date.

The interest is calculated for the entire month if the capitalization date is not there.

On reversal it does not takes the WBS ELEMENT with the Capitalization date.

any solution for this.