PPDS: DS Planning Board Queue time

733 Views

Hello SAP Experts,

In the DS Planning board in PPDS, the queue time is not being displayed in the operation chart / Network View operations.

The Std Queue time + Min. queue time are maintained at several workcenters level. These queue times are correctly maintained in the PDS as well as:

  • Ave. Min.Interoperation time
  • Min Interoperation time.

I am using the standard DS planning board profile which maintains for the different operations graphical objects the graphical element " 4 - Queue time" as brown

Therefore I am expecting therefore, I was expecting to witness the queue time between operations in the planning board. In fact it is also mentionned in the planning board legend.

- Is it normal ?

Thank you for your help,