I am running lead time scheduling.
Scheduling and Capacity requirement is on
Control key PP01 - Scheduling is active
Backward Scheduling
Material production details - 9 days will be taken for completing on lot of 200 qty. (don't consider weekends)
PIR = 01.08.2022 = 1000qty
000 Scheduling margin key
MRP Result - Planned order created on requirement date itself = 01.08.2022
Expectation - Planned order should create on 23.07.2022 - 9 days before requirement.
Is my expectation is correct or wrong. Please explain