Production readiness report

92 Views

Hi

There are tons of reports on production but nothing is ions full fledged report

As a production planner, I want to see planned orders/ production orders ready for next week ( basic start date filter in coois) where no problem exists capacity or component shortage . It should show all orders with basic start date range and a colum showing no capacity shortage , no component shortage . If it shows components shortage , if I click that line it should show which component is shortage and reason so that I have 1 week to make it right. If all good, a mass tool to release the order.