on 06-27-2022 12:21 PM
Hi Experts,
For our customer we want to do consumption of some components after the production order has completely been confirmed and delivered.
When I go to MIGO and try to do the goods issue for the components i get the message that there are no selectable items.
When I try it in our QAS system I am able to do the goods issue when the order is partially confirmed, but not when it is Final confirmation. Is there a way we can still do the goods issue for these components? Am I missing a custo setting?
Thanks!
Hi Ostyn,
Kindly check weather in confirmation parameters clear open reservation is activated, if yes then there might be a possibility that final issue indicator was flagged for all reservation items while confirming the order,hence you are getting that message while preforming goods issue using migo.
Regards
Dhaval
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |