Consumption of components on production order after order is completely confirmed and delivered

0 Kudos

Hi Experts,

For our customer we want to do consumption of some components after the production order has completely been confirmed and delivered.

When I go to MIGO and try to do the goods issue for the components i get the message that there are no selectable items.

When I try it in our QAS system I am able to do the goods issue when the order is partially confirmed, but not when it is Final confirmation. Is there a way we can still do the goods issue for these components? Am I missing a custo setting?

Thanks!

Accepted Solutions (0)

Answers (1)

Answers (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hi Ostyn,

Kindly check weather in confirmation parameters clear open reservation is activated, if yes then there might be a possibility that final issue indicator was flagged for all reservation items while confirming the order,hence you are getting that message while preforming goods issue using migo.

Regards

Dhaval