Hi,

(I'm working on automation with apps Manage Your Test Processes and Test Your Processes (Manage Your Solution) to automate selected test processes.)

I cannot execute any test plan in Test Your Processes app today. The status still shows "In Process" and 0% Coverage. I noticed this issue yesterday (27.06.2022).

I tried to create a new short test process but with the same result.

sap-tat-screen-issue.jpg

Is there any maintenance or is it a temporary know issue?

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Sonam
Product and Topic Expert
Product and Topic Expert

Hi Kamil,
There could be the following reasons for this issue-
1. Please check your test user, if it is set up properly with the correct username and password. If you have recently changed your password, please update the same in the test automation tool as well.
Please check the below blog to check if the tool and test user are setup properly-
https://blogs.sap.com/2019/05/27/how-do-i-set-up-the-test-automation-tool-in-sap-s4hana-cloud/
2. If you have scheduled more than 40 test plans, then the new test plans will only execute once the other 40 are sent for execution.
3. There could be a temporary issue. Please re-execute and let us know the status.

Regards,
Sonam

kamilfilochowsk
Explorer

Hi Sonam,

it could be point 3 or 1 (maybe the person who in charge of managing user settings changed the password and updated it now). Execution of test plans works correctly today. Thanks for your reply. It may be useful for the future.

Regards

Kamil