Good afternoon,

We are having some problems while working in DDMRP because the SAP we are using is an old version. We calculate buffer levels in DDMRP and we can examine this with the Fiori "Manage Buffer Levels" application. According to the "Net Flow Position", a "Proposed Quantity" is also calculated. But we don't know what to do with this "Proposed Quantity". In the applications in Fiori, we do not have buttons such as "Create Order" or "Expedite Supply" or a column such as "Action". What should be the next step from the buffer calculation?

Kind regards,

Accepted Solutions (0)

Answers (2)

Answers (2)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

I would need more information to help you. Is your stock below the reorder point calculated by DDMRP? Did you see any error for this material when MRP was executed?

Can you post some screenshots of MD04?

Regards,
Caetano

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

You generally use DDMRP to calculate the buffer, which is nothing else than a safety stock, a reorder point and a maximum stock level. After that, you should run MRP and it will create replenishment proposals to ensure that the buffer is covered.

Best regards,
Caetano Almeida

buseevsenn
Discoverer
0 Kudos

Hello,

Thank you for your answer. As you stated, after calculating the buffer, we ran MRP for the relevant material, but when we checked it from MD04, unfortunately, no replenishment offers were created. Do we need to do one more thing for the replenishment to create?

Kind regards,