on 06-21-2022 7:22 AM
Dear Experts
For a Finished material, with procurement type E, the procurement team has raised PR and PO of total 8 pcs . Due to this , the system identifies no material shortage, therefore , even though the PIR is created for 2 pcs , the system is unable to create planned orders.
The material needs to be corrected to procurement type X. However , we seek to ensure that the PR and PO, do not interfere with the Planned independent requirement, specifically for this material .
Requesting for valued suggestion.
Thanks and regards
Ayaz
Hello Ayaz
If you don't want this PR/PO to be relevant to MRP, perhaps you should use a storage location MRP area to plant it separately.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Caetano
Thanks a lot 🙂
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.