on 06-16-2022 2:53 PM
The 'Future planned price 1', field 'MBEW-ZPLP1' is not available in Mass change material for update.
Currently the changes for prices are not supported by the "Mass Maintenance Product" app as this could lead to inconsistencies.
The reason why the planned price cannot be updated through Mass change material app is explained in below note ,
Note323892 - MASS: Cannot select currency fields
Please use app 'Manage material valuations' which is dedicated for the price changes
Also refer to the below KBA for the same
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.