on 02-22-2017 1:03 PM
Hi All,
While releasing Forecast from DP to SNP without Period Split, I noticed that few initials weeks have Forecast for seven days while after few weeks its only released on 1st day of the week ( i.e. Monday).
Note:
1. No period Split has been maintained in Release Profile or Product Master.
What can be the possible reasons for such behavior?
TIA 🙂
Hi Lalit,
If there is no period split profile and the forecast exists in DP planning books for the entire range/buckets then you can check the location calendar , may be it could be because of non working days.
Check if your badi implementation of /SAPAPO/SDP_RELDATA is not interfering here.
Hope this helps.
Thanks & Best Regards,
Sonali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.