GI for process order

kalidindi_varma
Explorer
0 Kudos

Hi

As per the business requirement the system should look for the stocks in all SLoc in the plant and consume while doing GI for the process order. please let me know if it possible? If yes, what are the settings required?

Thanks & Regards,

Varma

Accepted Solutions (0)

Answers (1)

Answers (1)

Raja_S_Reddy_B
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Varma
If no Issue Storage location is maintained, System will look at the Stock of all the Storage locations in the Plant, during the Availability check. Hope, this Helps. Let me know, if you still have any questions.
Thanks & Regards : Raja