Discontinuation data is maintained in material master and BOM. The discontinuation date is in the past.
when I plan header material (MPS M0) with MD41, it works perfectly and demands fall on fallow up material but when I use MD51 It does not work, and demands fall on discontinued material.
follow up and discontinued materials have MRP type P3.
why is it so? Discontinuation not working for T code MD51 ( project level planning)
Please help