Hello,

We have a special casuistry in one of our companies in which a material processing is carried out in a subcontracted supplier to obtain the finished product to be sold to the customer.

At the moment, to place the order to the subcontract supplier, we indicate the item category "L" without any account assignment.

We want to control the stock at project level, so we could allocate these purchases to the project.

However, when we make the account assignment in the order to "Project", the stock becomes "Irrelevant to stock" so the stock valuation for these materials is not displayed from the stock applications.

Is there any way of displaying the stock valuation when it is allocated to Project? From the project I understand that yes, through the project procurement management, but this application does not offer the real valuation of the stock in the project.

Thank you very much,

Regards.