budget will block the on the time of Release PR as of the value maintained in PR.

0 Kudos

MY Client requirement is budget will block the Fund on the time of Release PR as of the value maintained in PR. Please help

Accepted Solutions (0)

Answers (2)

Answers (2)

iklovski
Active Contributor

Well, yes, obviously. Sorry, that I misunderstood you. This is the prudence concept in PSM-FM. All documents consuming the budget begin to reserve it at the beginning of their cycle and not at the end in order not to find yourself in a situation where the document is prepared and cannot be released, due to lack of budget. Otherwise, you would face a situation where, in theory, hundreds of PR can be created, and only two of them can be released.

iklovski
Active Contributor
0 Kudos

Hi,

This is standard behaviour. What is the problem exactly?

Regards,

Eli

0 Kudos

Hi Eli,

Goodday,

Budget is blocking on the time of creatioin PR insted of PR release .