on 05-12-2022 9:32 AM
Dear all,
I want to post a goods issue from outbound delivery (OBD). I have available quantity in the project stock. I also entered the WBS number in the OBD.
But I get error M7 021 - Deficit of BA Unrestricted-use 2.000 KG : 2000006 5000 SIT 0000000035.
How to tell the system to use the project stock?
Best
Peter
Please carry out the below steps
My preference would be to change the item category configuration to consider project stock and needless to say, you need to assign this item category to your sale order type in VOV4
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Couple of questions:-
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
If its in a normal stock then transfer the same material to Project stock first, then create a reservation with ref to the WBS code, and issue the same., or you can directly issue the material on WBS using movement type 221
this should work.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
pls check whether the same stock is reflecting in MBBS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.