CK11N material cost estimate BOM pick up issue in server

Dear All,

Am facing the following issue,say Finished good A..This same FG material is available in Development,quality and production server. But when CK11N is executed for this FG material,in dev server it picks up all the BOM materials for this FG,like all sub SFGs,ROH,packing all,as created in BOM..But in Quality and production server it is not picking all components for the same FG..It picks FG and shows only 2 components.Not showing other components in costing structure panel left side. Kindly help with it..!!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 28, 2017 at 04:34 AM

    Dear

    In CS02 check costing relevancy of BOM. put X on costing relevancy (100%).

    Regards

    Prasad

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 28, 2017 at 08:56 AM

    Dear Prasad,

    Thanks for your reply. The problem was it was marked as "Bulk material" in MRP 2 view. I removed the tick,now it's working.

    Add comment