on 04-20-2022 7:03 PM
If I have a critical permission risk that has an object with multiple fields, and I list all of these fields in the risk , does this lead to a greater load on the SAP system or will this impact performance in anyway?
Hi marthom91
it will not significantly impact the performance. I would not be afraid here;)
If you limit the number of fields all skipped will be treated as any value - this may lead to false positive. This is something we try to avoid. It is better to have more fields (assuming their are important from authorization perspective) then less fields and have false positive.
Thanks,
Filip