Skip to Content
0
Mar 24, 2022 at 04:52 PM

Production Order Cancelled - New MRP Wizard

143 Views Last edit Mar 25, 2022 at 08:25 AM 2 rev

Hi, we accidently raised a consolidated production order which we have since cancelled. I tried to run a new wizard to raise all the individual production orders, but all the sales orders are not available to select, as I guess the system thinks they have been used already; when we made the mistake. Is there a way to get SAP to see that the production orders still need to be raised in this scenario? I tried running an MRP wizard on the item, but it won't show production orders in the recommendations either. Is there something more we should do, other than cancel the production order that was raised in error, how do we get SAP to know that it still needs production orders?

Thanks in advance