Hi Expert,

We have a performance base Strategy Plan, in IP10 when we choose "Start in Cycle" and choose "Select Package" to set start offset, Due packages are displayed as 500, 1000, 1500, 2000........ series

how to reduce the frequency of this series such as 100, 200, 300, 400......?

Is there any way to Mass restart these plans with Start in Cycle by setting offset? (more than 200 plans)

Thanks

Ashok M

Accepted Solutions (0)

Answers (1)

Answers (1)

BalaAP
Active Contributor
0 Kudos

Hi, You may have to examine following options:

1) Mass change MCH01. But this requires activating specific business function using SFW5.

2) SHDB or LSMW or BDC to change bulk entries.

You may have to carefully approach the options, since you may have call objects which are already generated for these plans...