Hey,

I am currently trying to build an Excel to SAP Export based on a SAP table. In this case I am trying to get the planned costs of projects based on their network plans.

I appreciate any help!

Thanks in advance

Accepted Solutions (0)

Answers (1)

Answers (1)

Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

The planned costs from Network Activity cost planning are stored in tables COSS and COSP. To make sense of it all you will need several more object definition tables. You can also use the standard SAP reports and output the results to a spreadsheet.