Hi,
I have found the option "Stock within horizon"
What does this mean?
What is the difference to only "Stock"?
BR
Simon
Hello Simon,
When you Select Stock Check with Horizon, You get a field to define Horizon as a number of days. stock check rules are influenced based on the horizon definition.
Example 1:If the requested execution start date is within the check horizon and there are no supplies to cover the demand then the system confirms the total requested quantities at the end of the check horizon.
Example 2: If the requested execution start date is beyond the Check Horizon then the system confirm the requested Quantity on the requested Execution start date.
By defining an availability check horizon, you specify the number of days (today plus a certain number of days) within which the system checks the demand against the supply, taking the working day calendar of the ship-from location into account.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.