why is the time in routing and production order different (as in the picture) when I run the production order, like there is an extra time that I didn't maintain in routing? where did that time come from?

notes:

-I have confirmed that the formula in the work center is correct

-breaks on capacity are also correct

-I have also attached a detailed picture of the scheduling on the production order, where the extra time occurs

can anyone help me?