02-17-2022 9:19 AM - edited 02-04-2024 2:48 AM
Hi
In S/4HANA Cloud I struggle to find the documentation of how to assign resources to a project using the scope items 35F and 4RF.
How do I link a resource to a user in S/4HANA and then to a project, so that the project is available under Manage My Time Sheet?
Thanks
Hi Thorben, Please follow best practice scope item 1Q4, to maintain the timesheet for the user/resource.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can use the Manage Assignments app to create, change, and delete assignments for resources and resource requests.https://help.sap.com/viewer/29cf986299714386847f4d4c9bb86994/2202.500/en-US/5f80a895eb194b55a216a096a2662a23.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.