When using Migration Cockpit for direct transfer of material master, is it possible to have the material number reassigned in S/4HANA (internal number assignment) or is this transferred 1:1 from ECC to S/4AHANA as standard? Awaiting your valuable inputs on it. Thanks.
Hi Ravi,
You can set to internal number range in mapping tasks, same as Migration Cockpit File/Staging approach.
Thanks,
Vincent