Restrict PO Changes after Partial Receipt of GRN

Anjan999
Explorer
0 Kudos

HI,

The client is expecting Block In s4hana Flexible workflow Purchase order changes after final Approval or Partial Receipt of GRN.

Full Receipt PO Change control is working correctly.

For Partial GRN scenario's is there any option to control further changes in PO?

Accepted Solutions (0)

Answers (2)

Answers (2)

ankurch
Active Contributor
0 Kudos

Hi There,

you can restrict changes in PO if partial GR/Full GR has been posted in the system, by using BADI - BADI_ME_PO_CUST.

in process check and post.

Thanks,

Anjan999
Explorer

Thanks Ankur Chauhan. For Full Qty GRN Posted Line Items, we have a standard message to control like below. For partial GRN Items, I need to restrict PO Changes Through BADI - BADI_ME_PO_CUST.

OMAS - 06-744 - Delivery of item & of document & already completed

ankurch
Active Contributor
0 Kudos

You can add your custom message - GR is posted, cannot make changes.

bhumi_1star
Active Contributor
0 Kudos

Hi,

Once you block PO Line Item, then system will not allow to do further GR.

But if you will not block PO Line Item, then will allow to do further GR for Partial Quantity.

If PO quantity is open , then system will allow for GR posting.

Bhumika

Anjan999
Explorer
0 Kudos

Requirement is After Partial GRN Flexible workflow Purchase order should not allow to do any changes in PO level .