Hi All,
I would like to change the Execution Finish data of an operation from a Production Order, but I can't.
I already tested all BAPI's below, but none of them worked.
BAPI_PROCORD_CHANGE
BAPI_ALM_ORDER_MAINTAIN
CO_XT_OPERATION_CHANGE
CO_SE_PRODORD_CHANGE
CO_EXT_ORDER_SCHEDULE_UPD
The function needs to be configured how RFC, because I call from an external system.
Could anyone help me?
If one of these BAPIs above was correct, is it possible to send me an example of filling it out, please?
Best Regards,