Hello Experts!

We found that one of our part numbers has different days in the Planned Deliv. Time, in the T.code MM03>MRP2 has 21 days and in the Info Record it says 49 days. My question is, SAP makes the decision and sends the PurReqs based in which Planned Deliv. Time? Or both should be the same?

Note: We only have one vendor set up.

My role is Planner Buyer.

Also, other quick question... The Planned Deliv. Time should include Lead time + Transit time?

Let me know your comments, really appreciated!