We are working on Schedule Agreement but our most of RM prices changed on quarterly basis, do i need to create new schedule agreement when price changes or let me know how i can handle this price change in same schedule agreement.
Hello balharam
You can activate time dependent pricing conditions in the schedule agreement type configuration - IMG: Materials Management -> Purchasing -> Purchase Scheduling Agreement -> Define Document Types:This way you'll be able to specify validity dates of pricing conditions in a scheduling agreement.
Best regards
Dominik Tylczynski