01-04-2022 6:05 AM - edited 02-04-2024 2:23 AM
Hi,
For HANA Database, after a Non-disruptive DR drill[doing DR drills when the production instance is running], is it possible to sync the secondary site without a full data shipping?
Regards,
Cheriyan,
If a secondary system/site is shut down and not used for a longer period of time like DR drill etc., unregister it first to prevent log volumes from accumulating on the primary system. However, in such a case a full data shipping will be necessary when the system reconnects.
Refer standard guide for more details.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.