Skip to Content

Note 2422691 - Side effect

Just to inform and share our case.

We faced an issue after installation of Note 2422691. The SNP heuristic run could not determine the PPMs.

Regards.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Mar 13, 2017 at 02:03 PM

    Hi Warner.

    I confirm that all the master data (material, PPM and T-Lane) are aligned, consistent. We just deactivate the note in order to make the heuristic work (assigning the PPM).

    Thank for your help.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 03, 2017 at 01:06 PM

    Hi Mauro,

    Could you please share the error message that you are getting?
    Is it happening when running Location heuristic?

    Best regards,
    Werner Hansen

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 07, 2017 at 12:52 PM

    Hi Warner.

    No error message, the heuristic runs and ends without errors. The system just can not link the PPM to the planned order created.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 09, 2017 at 01:35 PM

    Hi Mauro,

    Please check that if there is neither a valid transportation lane (for procurement type F; external procurement) nor valid PPM/PDS (for procurement type E; in-house production), the system creates an SNP stock transfer or SNP planned order with no reference to a source of supply. The same applies if there is no product in the source location of the transportation lane.
    More at: https://help.sap.com/saphelp_ewm70/helpdata/en/da/8df3128121304a8dc1eef961a6d3a8/frameset.htm

    Best Regards,
    Werner Hansen

    Add comment