Hi Time Expert,
We have configured a sub-type counting non-working days.
When this absence is calculated over a half-day of a nonworking day, the system counts down a full day.
Example :
Considering that Sunday January 23, 2022 is nonworking, we wish to ask for a calendar absence from 8:00 a.m. to 12:00 p.m.
How do I get the system to count 0.5 days instead of 1 day?