Hi,

I am using MRP type VV for forecast based planning. I have posted consumption of project stock (WBS assigned) againt several maintenance orders. But when I check consumption history in Material master forecasting view, I do not see any value for these posting as consumption. I am able to see other Goods issue which are not specific to any project or sales order.

in OMJJ, for Movement type 261 consumption is set to blank in update control.

Does SAP consider project stock consumption as consumption history in forecast based planning? Please advise.

Regards,

Atul

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

Withdrawals from the sales order stock or project stock do not update the material consumptions. See SAP Note 310183 for more information about this.

Regards,
Caetano