on 12-02-2021 5:19 PM
Since the 2111 release upgrade is close, and this time the Q2P transport freeze is Tuesday(10/26) very near. Our financial month-end-closing is plan to start at Oct. 30th, and we need to adjust the overhead
This changes should be recorded in the current business change project and will only be available for import in P once the transport lock period is closed after the P upgrade. There is no individual transport raised for this configuration as far as i know
Maybe you can stop the validity of the old rates to 30th of October and create new rates form 31 onwards that could be transported before the transport lock is raised.