Work orders are not showing material cost, where component is already selected.

We have created a work orders with component, it has been notice that costing option was not selected for order type, due to that reason orders not showing cost related to the material, so how we can let system to show the cost of these work orders.

thanks

ERPSUPP.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    Feb 21, 2017 at 02:54 PM
    Add comment
    10|10000 characters needed characters exceeded

  • Feb 21, 2017 at 12:02 PM

    ERPSUPP,

    What do you man by "costing option was not selected for order type"??

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 21, 2017 at 12:50 PM

    PeteA,

    It means in SPRO costing parameter, plan var cal & Actual var Calc was not mentioned.

    Thanks

    ERPSUPP

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 22, 2017 at 08:43 AM

    Dear PeteA

    Yesterday i found this same note and implemented and it worked.

    Thanks