hi,

I would like to check the capacity when a production order is created on SAP.

So, if in the week in which i would put my order there are all the materials but there is no capacity available, the system should suggest the first day available for capacity.

I have searched on internet and i have found the transactions opjk and opu3, but i have no access and i can't use them. So i would ask in which other way i can set this capacity check based on finite capacity?

i have already set "Relevant for finite scheduling" in all the work centers, but it seems it doesn't work in the capacity requirements check.

Thank you,

Katia

former_member763929
Participant
0 Kudos

Thank you for visiting SAP Community to get answers to your questions. Since this is your first question, I recommend that you familiarize yourself with Community Q&A , as the overview provides tips for preparing questions that draw responses from our members.

Should you wish, you can revise your question by selecting Actions, then Edit.

By adding a picture to your Profile you encourage readers to respond.

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Katia

Capacity availability check should be enabled for your order type in the customizing transaction OPJK. You will need to request access to this transaction or ask someone to activate capacity availability check for your order type in this transaction.

Regards,
Caetano

0 Kudos

Hello Caetano,

thanks a lot for the answer.

But, at the moment I don't have authorization to activate OPJK transaction, so I'm looking for a different way to do this capacity availability check.

Regards,
Katia

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Katia

You cannot use this feature if it is not active in customizing.

Regards,
Caetano