on 11-24-2021 10:58 AM
hi,
I would like to check the capacity when a production order is created on SAP.
So, if in the week in which i would put my order there are all the materials but there is no capacity available, the system should suggest the first day available for capacity.
I have searched on internet and i have found the transactions opjk and opu3, but i have no access and i can't use them. So i would ask in which other way i can set this capacity check based on finite capacity?
i have already set "Relevant for finite scheduling" in all the work centers, but it seems it doesn't work in the capacity requirements check.
Thank you,
Katia
Hello Katia
Capacity availability check should be enabled for your order type in the customizing transaction OPJK. You will need to request access to this transaction or ask someone to activate capacity availability check for your order type in this transaction.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.