Scheduling lines generating on MRP run

0 Kudos

Hi All,

When we run Tcode MD02, scheduling lines are generating automatically for the scheduling agreement even if the agreement is not released. please advise if we can restrict the schedule line creation in MRP run if the agreement is not released. Kindly assist.

Thanks.

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

As per SAP KBA 1941601 - Non released purchase order and scheduling agreements appear in MD04, this is the system standard behavior. You might need to implement a BAdI if you don't want this agreement to be considered by MRP.

Regards,