hello Gurus.

we implemented a scenario of MM scheduling agreements type LP which are for Intercompany.

so one legal unit creates a SA, schedules dates for the whole year and the supplying legal unit is supposed to supply the materials according to the dates in scheduling.

in MD04 all the scheduled dates appear accordingly but the issue is that when the supplying unit creates a delivery with VL10D, also the dates for future deliveries appear and if there is a stock, the delivery is created for material that is not expected to be delivered yet.

How can we prevent this from happening?

I tried various selection screens scenarios in VL10D but it did not help.