No link to the backend system

Hi

When I am trying to tranfer the PR from R/3 to EBP system, I am getting the following error:

<b>No link to the backend system at the moment. Inform system admin.</b>

I maintained the profile, and the combination of the material group and purchasing group to that profile in R/3 system.

Can anybody let me know where the devil is...?

Regards

Vangala Reddy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 10, 2006 at 11:45 AM

    Hi Muralidhar,

    Did you maintain RFC connection between SRM and R/3 ?

    What exact steps in SRm and R/3 did you perform so far to implemnt the plan driven procurement scenario ?

    Kind regards,

    Yann

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Muralidhar,

      Since you have changed the logical system name, are you able to run a complete flow from SRM to R/3 ?

      Always tricky when you change logical system name after having configured partially the system...

      Kind regards,

      Yann