How to restrict to the Complete(Business) of reversal once settlement is done.

Dear Expert,

How to restrict to the Complete(Business) of reversal once settlement is done in Plant maintenance Oder (IW31/IW32)

Thanks,

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 21, 2017 at 10:16 AM

    You could manually set a user-status after settlement has been performed. And this user-status could block CLSD reversal.

    If you want this to happen automatically, then you would need to control this via development.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Dear Mr.peter,

      This is an audit requirement.on this way we can open the order after the Complete(Business) of reversal once settlement is done .Isn't it?

  • Feb 28, 2017 at 10:45 AM

    It depends on each company/country..