Skip to Content
0
Oct 11, 2021 at 07:54 AM

Optimization not consider second Manufacturing Plant

236 Views Last edit Jan 11, 2023 at 11:08 AM 2 rev

Hello Expert,

We are working optimization scenario with IBP. Business Supply chain design as below

Two customers -C1 & C2 and Manufacturing Plants-F1 & F2. Both customers demand supply from both plants with 4 & 6 Ratios.

Run the Optimization Customer received done as "Non-Delivery Cost Rate for Customer Demand" and its working file while checking the Production SoS its consider only F1 Plant resource and Plant-F2 resource did not utilize, no Utilization %.

Please help to know the solution how to use second plant resource with optimization run.

Thanks In advance

Rajesh Tiwari