Dear Experts,


In production order 40638 (as attached), we use another extra material of 1 kg. And after using extra material the system has done addition of both material price to the finish good material price instead of average price .

Due to this difference it goes into the WIP variance account .

We want to know why this happens ? And is there anything that we need to take care of in the future to avoid this ?

Please see attached screenshots for your easy reference.

Actual calculation should be done as => 235010.73 / 2038 = 115.31439

Currently the system is showing unit price as => 115.371 + 209.060 => 324.375 in Receipt of production instead of 115.314 due to which the variance is showing. Kindly advise


Regards,
Prashant P.

production-order.pngvarince-difference.pngrelationship-map.pngreceipt-of-production.pngreceipt-of-production.png

Accepted Solutions (0)

Answers (1)

Answers (1)

ANKIT_CHAUHAN
Product and Topic Expert
Product and Topic Expert
0 Kudos

Dear vikramsoundankar.soundankar,

Kindly check and verify whether SAP Note 2727909 helps in this regards.

Kind regards,

ANKIT CHAUHAN