We have existing work orders without showing material cost as cost element was configured later.

We have existing work orders without showing material cost as cost element was configured later, so now how we can get the cost of all orders ?

Thanks

ERPSUPP

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 23, 2017 at 07:46 AM

    ERPSUPP,

    Back-out the old material postings and make new postings.

    PeteA

    Add comment