Hello everyone, I hope you are all good.

I'm having some problems with my maintenance plans. We are programming using the same parameters, but when we close and confirm the maintenance orders, some of them automatically generate the next ones and others do not. We checked all of them, and the plans are using the same informations. In this case, we have been using IP10 and IP30, to start this orders. Can you help us with some information ?

Accepted Solutions (0)

Answers (2)

Answers (2)

peter_atkin
Active Contributor
0 Kudos

Igor,

Thanks for the images.

Can you explain what is wrong with this plan?

PeteA

peter_atkin
Active Contributor
0 Kudos

Igor,

Check the call horizon settings in the maintenance plans. If this is set to 0% then it will create the next order immediately.

PeteA

0 Kudos

hi Peter, we are using 1%.

peter_atkin
Active Contributor
0 Kudos

So thats very close to 0% and will also create the orders VERY soon after TECO of the previous order.

PeteA

0 Kudos

Yes Peter, in some cases the orders are ok, the next orders are oppening normally, but in some cases not. The orders are waiting for our actions.

peter_atkin
Active Contributor
0 Kudos

Do the orders that are OK have shorter maintenance periods that those that are NOT OK?

Can you give some examples, possibly showing the IP10 calls?

PeteA

0 Kudos

Hi Peter, the periods are the same between the plans. I'm sending an example where the next order is not oppening.

0 Kudos

Here I'm sending a picture showing the horizon and intervals.