Defaulting and removing Reference Date in PM Order

former_member762204
Discoverer
0 Kudos

Hi gurus,

For defaulting Reference date, we are using SPRO settings ( 1- Creation date, 2- basic Start date, 3- Basic Finish date)

Is there any way to remove defaulting date and keep reference fields as blank in order to allow users to enter date and time fields manually

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

Gajanan Naik,

For future reference; you will get a better response if you also tag your posts with: PLM Enterprise Asset Management (EAM)/Plant Maintenance (PM).

It doesn't look like you can configure the system to have a blank date.

But you could use an Implicit Enhancement at the bottom of LCOIHFG5->ADDAT_PROPOSAL to manipulate the reference data. Talk to your ABAP Team who should be able to help.

PeteA